Contract No: HK/2015/01 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and Testing Work (Stage
3) Environmental
Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 Fep-06/356/2009, FEP-07/356/2009 and
FEP-08/356/2009 Quarterly Environmental Monitoring
and Audit Report
- December 2018 to
February 2019 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and
Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
22 May 2019 |
2.2 Scope of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
2.5 Principal Work and Activities
5.5. Review of the Reasons for and the Implications of
Non-compliance
5.6. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST OF TABLES
Table II Principal Work
Activities for Contract no. HK/2009/02
Table IV Principal Work
Activities for Contract no. HY/2009/19
Table V Principal Work
Activities for Contract no. HK/2012/08
Table VI Principal Work Activities for Contract no. HY/2010/08
Table 2.1 Schedule 2 Designated
Projects under this Project
Table 2.2 Details of Individual
Contracts under the Project
Table 2.3 Contact Details of
Key Personnel
Table 2.5 Principal Work Activities for Contract no. HK/2009/02
Table 2.7 Principal Work
Activities for Contract no. HY/2009/19
Table 2.8 Principal Work Activities for Contract no. HK/2012/08
Table 2.9 Principal Work Activities for Contract no. HY/2010/08
Table 3.1 Noise Monitoring Stations
Table 3.2 Air Monitoring
Stations
Table 3.3 Marine Water Quality
Stations for Water Quality Monitoring
Table 3.4 Marine Water Quality
Monitoring Frequency and Parameters
Table
3.5 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/02
Table 4.3 Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.4 Noise Monitoring Stations for Contract no. HY/2010/08
Table 4.6 Air Monitoring Station for Contract no. HK/2009/02
Table 4.8 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.9 Air Monitoring Station
for Contract no. HK/2012/08
Table 4.10 Air Monitoring Stations for Contract no. HY/2010/08
Table 4.12 Water Monitoring Stations for
Contract no. HK/2009/02
Table 4.13 Water Monitoring Stations for Contract no. HK/2012/08
Table 4.16 Water quality monitoring Stations for Contract no. HY/2010/08
Table 4.17 Enhance Dissolved
Oxygen Monitoring Stations for Contract no. HY/2010/08
Table 4.18 Details of Waste
Disposal for Contract no. HK/2009/01
Table 4.19 Details of Waste
Disposal for Contract no. HK/2009/02
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details of Waste Disposal for Contract no. HY/2009/19
Table
4.22 Details of Waste Disposal for
Contract no. HK/2012/08
Table
4.23 Details of Waste Disposal for Contract no. HY/2010/08
Table 6.1 Cumulative Statistics
on Complaints
Table 6.2 Cumulative Statistics
on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization
Chart
Figure 3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise Monitoring Graphical
Presentations
Appendix
4.2 Air Quality Monitoring Graphical
Presentations
Appendix
4.3 Water Quality Monitoring Graphical
Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 7.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
Table II Principal Work Activities for Contract no.
HK/2009/02
December 2018 |
January 2019 |
February 2019 |
Removal of TWCR4 |
Trimming
of seabed profile at TWCR4 |
Placing
berm block and rock armour at TWCR4 |
Table IV Principal Work Activities for Contract no. HY/2009/19
December 2018 |
January 2019 |
February 2019 |
Seawall block reinstatement near Box Culvert T1 |
Seawall block reinstatement near Box Culvert T1 |
Seawall block reinstatement near Box Culvert T1 |
Table V Principal Work Activities for Contract no.
HK/2012/08
December 2018 |
January 2019 |
February 2019 |
Nil |
Nil |
Nil |
Table VI
Principal Work Activities for Contract
no. HY/2010/08
December 2018 |
January 2019 |
February 2019 |
Nil |
Nil |
Nil |
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Complaints, Notifications of Summons and Successful
Prosecutions
An EPD complaint
was referred to the ET on 16 January 2019 (CASE Ref: H08/RS/00001488-19,
H08/RS/00001532-19, and H08/RS/00001663-19). The complainant reported that
milky water discharge was found at the Victoria Harbour,
near Causeway Bay Typhoon Shelter on 12 January 2019.
ET confirmed with
the WDII Resident Site Staff that the concerned area was located out of the site
area of Contract No. HK/2009/02 and the Contractor of HK/2009/02 had no
activity at the area concerned on 12 January 2019.
ET confirmed with
the CWB Resident Site Staff that no construction works was conducted by the
contractor of HY/2010/08 at Victoria Harbour, near
Causeway Bay Typhoon Shelter on 12 January 2019 at around noon.
Despite no
construction activity was conducted under Contract HK/2009/02 and HY/2010/08 on
the concerned date and location as confirmed with corresponding Resident Site
Staff, in view of public concern, the Contractor of Contract HK/2009/02 and
HY/2010/08 were reminded to review the on-site drainage system and the
operation of wastewater treatment system. The Contractor of Contract HK/2009/02
and HY/2010/08 were also reminded to provide mitigation measure such as
deployment of silt curtain to enclose the works area if any marine activity to be
conducted at the concerned area.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009,
FEP-03/356/2009,
FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from 27th December 2018
to 26th February 2019.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project Background – summarizes background and scope of the project, site
description, project organization and contact details
of key personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all
monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results obtained in the
reporting period.
Section 5 Compliance Audit – summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes
the relevant cumulative construction impact due to the concurrent activities of
the concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2.
The
study area encompasses existing developments along the Wan Chai, Causeway Bay
and North Point shorelines. Major land uses include the Hong Kong Convention
& Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan
Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club
(RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and
commercial and residential developments.
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and facilities,
including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land
formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
·
Reprovisioning / protection of the existing facilities and structures affected by the
land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
·
Upgrading of hinterland storm water drainage system and sewerage system,
which would be rendered insufficient by the land formation works mentioned
above
·
Provision of the ground level roads, flyovers, footbridges, necessary
transport facilities and the associated utility services
·
Construction of the new waterfront promenade, landscape works and the
associated utility services
·
The Trunk Road (i.e. CWB) within the study area and the associated slip
roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains
from Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1 Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2 The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 (Completed) |
DP1, DP2 |
25 August 2011 (Completed) |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 (Completed) |
DP1 |
13 July 2011 (Completed) |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
10 March 2014 (Completed) |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II Central-
Wan Chai Bypass at Wan Chai West |
DP1,DP2, DP3 |
5 March 2013 |
HY/2011/08 |
Central-Wan Chai Bypass (CWB) –
Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key personnel
and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for
WDII |
Chief Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Chief Resident Engineer |
Mr. Dennis Norton |
3912 3188 |
3912 3010 |
|
Chief Resident Engineer |
Mr. S. K. Lo |
3912 3288 |
3912 3010 |
||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2566 2192 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
|||
Construction Manager |
Mr. Tom Tong |
3557 6415 |
|||
Environmental Officer |
Mr. Gabriel Wong |
6114 9590 |
|||
Environmental Supervisor |
Mr. Gordon Lai |
6145 6365 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
3757 8901 |
Site Agent |
Mr. William Luk |
3758 6868 |
|||
Deputy Site Agent |
Mr. Andy Chan |
9879 4325 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Assistant Environmental Officer |
Mr. James Chan |
9602 2911 |
|||
Construction
Manager (Marine) |
Mr. Wingo Wong |
9608 6366 |
|||
Construction Manager (Land) |
Mr. Mark Mak |
9356 4421 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Construction Manager (Ext. Works) |
Mr. Paul Wan |
6629 4652 |
|||
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project Director |
Mr. C. N. Lai |
9106 5806 |
2877 1522 |
Project Manager |
Mr. George Cheung |
9268 1918 |
|
||
Environmental Officer |
Mr. James Ma |
9130 9549 |
|
||
Environmental Supervisor |
Mr. Y. L. Ho |
9856 5669 |
|
||
China State |
Contractor under Contract no. HY/2010/08 |
Project Director |
Mr. Chris Leung |
3467 4299 |
2566 8061 |
Project Manager |
Mr. Chan Ying Lun |
3418 3001 |
|
||
Site Agent |
Mr. Thomas Lui |
3557 6452 |
|
||
Marine Manager |
Mr. Nickael
Chan |
3557 6333 |
|
||
Construction Manager |
Mr. Tom Tong |
3557 6415 |
|
||
Environmental Officer |
Mr. Gabriel Wong |
3557 6466 |
|
||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team
(ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for Contract no.
HK/2009/02
December 2018 |
January 2019 |
February 2019 |
Removal
of TWCR4 |
Trimming
of seabed profile at TWCR4 |
Placing berm block and rock armour at TWCR4 |
2.5.2. Contract no. HY/2009/19 was
commenced on 24 March 2011. During this reporting period, the principal work
activities for Contract no. HY/2009/19 are summarized as below:
Table
2.7 Principal Work Activities for Contract no. HY/2009/19
December 2018 |
January 2019 |
February 2019 |
Seawall block reinstatement near Box Culvert T1 |
Seawall block reinstatement near Box Culvert T1 |
Seawall block reinstatement near Box Culvert T1 |
2.5.3. Contract no. HK/2012/08 was
commenced on March 2013. During this reporting period, the principal work
activities for Contract no. HK/2012/08 are summarized as below:
Table
2.8 Principal Work Activities for Contract no. HK/2012/08
December 2018 |
January 2019 |
February 2019 |
Nil |
Nil |
Nil |
2.5.4. Contract no. HY/2010/08 was
commenced on 21 March 2013. During this reporting period, the principal work
activities for Contract no. HY/2010/08 are summarized as below:
Table 2.9 Principal Work Activities for Contract no.
HY/2010/08
December 2018 |
January 2019 |
February 2019 |
Nil |
Nil |
Nil |
2.5.5.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Footbridge
at Ex-Harbour Road Sports Centre* |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
Remarks*: With respect to
the demolition of Ex-harbour Road Sports Centre, the respective noise
monitoring station M1a- Harbour Road Sports Centre were finely adjusted on 16
and 25 May 2017 and thereafter to the Footbridge at Harbour Road Sports Centre
for noise monitoring.
Noise Monitoring Parameters, Frequency and Duration
3.1.2. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900
hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3. Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
one set of measurements between 0700 and 1900 hours on
normal weekdays.
3.1.4. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO
shall be obtained by the Contractor.
3.1.5. Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
·
One set of measurements
between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on
public holidays.
·
One set of
measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. Immediately
prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. Measurements may be accepted as valid only
if the calibration level from before and after the noise measurement agree to
within 1.0 dB.
3.1.7. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2 Air Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Site Office** |
North Point |
CMA2a |
Causeway Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the Prevention of Cruelty to
Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks*: As per the ENPC
meeting in January 2011, the monitoring stations CMA3a - Future CWB site office
at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work
Area were renamed as remark.
Remarks**: The location ID of monitoring station CMA1b was updated as “Oil
Street Site Office” in April 2013.
Remarks***:
The station ID and monitoring location was updated in December 2014 with
respect to monitoring station relocation.
Air Monitoring Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5 High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 - 1.7 m3 per
minute adjustable flow range;
·
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable of providing
a minimum exposed area of 406 cm2;
·
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped with a
shelter to protect the filter and sampler;
·
incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
equipped with a flow
recorder for continuous monitoring;
·
provided with a
peaked roof inlet;
·
incorporated with a
manometer;
·
able to hold and
seal the filter paper to the sampler housing at horizontal position;
·
easily changeable
filter; and
·
capable of operating continuously for a 24-hour period.
3.2.6 Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement / Analysis
3.2.7 A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
3.2.8 An
alternative non-HOKLAS
accredited laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8
February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement performed by
the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the accuracy
of measurement results.
3.2.9 Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
3.2.10 After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11 All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
3.2.12 Odour patrols along the
shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working
Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo
Working Area, or when there is dredging of the odorous sediment and slime at
the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols
will be carried out at bi-weekly intervals during July, August and September by
a qualified person of the ET who shall:
·
be at least 16 years
of age;
·
be free from any
respiratory illnesses; and
·
not be allowed to
smoke, eat, drink (except water) or use chewing gum or sweets 30 min
·
before and during
odour patrol
3.2.13 Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure 3.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
·
0 - Not detected. No
odour perceived or an odour so weak that it cannot be easily characterized or
described;
·
1 - Slight
Identifiable odour, and slight chance to have odour nuisance;
·
2 - Moderate
Identifiable odour, and moderate chance to have odour nuisance;
·
3 - Strong
Identifiable, likely to have odour nuisance;
·
4 - Extreme Severe
odour, and unacceptable odour level.
3.2.16 The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.
3.3.1. The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out
during the proposed dredging works to ensure the compliance with the water
quality standards.
3.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April – September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water
Quality Monitoring Stations
3.3.3. Water quality monitoring was undertaken at WSD salt
water intakes and cooling water intakes along the seafront of the Victoria
Harbour. The proposed water quality
monitoring stations of the Project are shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3
Marine Water Quality Stations for Water
Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water
Intake |
|||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water
Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
Cooling Water Intake / WSD Salt Water Intake |
|||
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt
water intake |
836268.0 |
816020.0 |
Remarks: - The cessation of seawater intake
operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was
then terminated since 17 May 2011.
-
4-week post construction water quality
monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012
and the water quality monitoring at WSD 10 and WSD15 were temporary suspended
since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 2012 onwards.
-
C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
-
C8 & C9 were
temporary suspended since 30 March 2013.
-
WSD7 and WSD20 water
quality monitoring were temporarily suspended from 27 Apr 2012.
-
C2, C3 C4e and C4w
water quality monitoring station was temporarily suspended since 24 Apr 2013
-
C5e and C5w water
quality monitoring station was temporarily suspended since 29 July 2013.
-
WSD21 water quality
monitoring station was temporarily suspended since 12 Mar 2014
-
WSD9 and WSD17 water
quality monitoring station was temporarily suspended since 8 Sep 2014 flood
tide.
-
The water quality monitoring station C1 shall
be associated with Contract No. HK/2009/02 upon commencement of marine works
under DP3 at WCR3 area
-
The water quality monitoring station RW21-P789
was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
-
The water quality monitoring was reverted to
previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25
January 2017 onwards.
Water Quality Parameters and frequency
3.3.4. Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
3.3.5. In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
3.3.6. The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table 3.4 shows the proposed
monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
3.4 Marine Water Quality Monitoring Frequency
and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline monitoring period |
Three days per week, at mid-flood and mid-ebb
tides |
Turbidity, Suspended Solids (SS), Dissolved
Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood and mid-ebb
tides |
Turbidity, Suspended Solids (SS), Dissolved
Oxygen (DO), pH, Temperature, Salinity |
After completion
of marine construction works |
Three days per week, at mid-flood and mid-ebb
tides |
Turbidity, Suspended Solids (SS), Dissolved
Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be measured in situ
whereas SS should be determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
3.3.7. The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
·
a dissolved oxygen
level in the range of 0-20 mg/l and 0-200% saturation
·
a temperature of
0-45 degree Celsius
3.3.8. It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A
submersible stirrer with reel and cable or an approved similar instrument).
3.3.9. Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
3.3.10 The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
3.3.11 Water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and Storage
3.3.12 Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as
possible after collection for analysis.
Water Depth Detector
3.3.13 A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
3.3.14 A portable
salinometer capable of measuring salinity in the
range of 0-40 ppt shall be provided for measuring
salinity of the water at each of monitoring location.
Monitoring Position Equipment
3.3.15 A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
3.3.16 All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
3.3.17 For the on site calibration of field equipment by the ET, the BS
127:1993, "Guide to Field and on-site test
methods for the analysis of waters" should be observed.
3.3.18 Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
Laboratory Measurement / Analysis
3.3.19 Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L
shall be collected at the monitoring stations for carrying out the laboratory
SS determination. The SS determination work shall start within 24 hours after
collection of the water samples. The SS determination shall follow APHA 19ed or
equivalent methods subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
3.3.20 The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
3.3.21 Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table
3.5 and Figure 3.1.
Table 3.5 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor
House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo Working Area |
3.3.22 The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be less than 3m, only the mid-depth
will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
3.3.23 During
dredging of the sediment at the south-western corner of the Causeway Bay
Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of
turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.24 The 24
hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water
quality monitoring station in front of the intakes during the dredging
activities. The monitoring system
include the turbidity sensor and data logger which is capable of data capturing
at every 5 minutes. The data shall be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy
monitoring at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.25 In
response to the Condition 2.18 of the Environmental Permit
no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored.
3.3.26 With
respect to the commencement of dredging works under HK/2012/08 and the
installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
3.3.27 The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
4.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in
Figure
2.1 and Figure
3.1. The monitoring results are presented in according to the
Individual Contract(s).
4.0.2. According to
EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by environmental permit No.
EP-356/2009 issued to Civil Engineering and Development Department”, and
marine piling works to be conducted by the Contractor of Contract no. HY/2009/19
from 28 January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
4.0.3. As confirmed by WDII RSS, the marine
construction works under Contract HK/2009/01 have been completed since 24 July
2017, the monitoring association with Contract HK/2009/01 and relevant
reporting has been ceased from November 2017. FEP-02/356/356/2009 under
Contract HK/2009/01 was surrendered on 19 April 2018.
4.0.4. As confirmed by CWB RSS, the marine
construction works under Contract HY/2009/15 and relevant reporting have been
completed by 19 June 2017, the monitoring association with Contract HY/2009/15
and relevant reporting has been ceased from November 2017.
4.0.5. As confirmed by CWB RSS, the marine
construction works under Contract HY/2010/08 and relevant reporting have been
completed by 21 September 2018, the air monitoring stations namely CMA3a - CWB
PRE Site Office and noise monitoring station namely M2b – Noon day gun area and
M3a - Tung Lo Wan Fire Station association with Contract HY/2010/08 and
relevant reporting has been ceased in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.1.1.
The
proposed divisions of noise monitoring stations are summarized in Table
4.1 below.
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/02
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre |
Reporting period of December 2018
4.1.2. One limit level exceedances were
recorded at M1a – Footbridge for Ex-Harbour Road Sports
Centre on 19 December 2018 in the reporting period.
Despite
loading of C & D materials was conducted by Contract HK/2009/02 around the concerned
location during the time of measurement, no major noise emanation from the works
was observed during monitoring. Meanwhile, breaking works was conducted under non-WDII-CWB
contractor next to the monitoring station and observed as the major noise contribution
during monitoring. As such, the exceedance was considered as not relate to Project
works under HK/2009/02.
Reporting period of January 2019
4.1.3. No action or limit level exceedance was
recorded in the reporting period.
Reporting period of February 2019
4.1.4. No action or limit level exceedance was
recorded in the reporting period.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.5.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.6.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.3 below:
Table 4.3
Noise
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria
Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
Reporting
period of December 2018
4.1.7 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of January 2019
4.1.8 Two limit level exceedance was recorded
at M6 – Hong Kong Baptist Church Henrietta Secondary School on 18 and 25
January 2019 in the reporting period.
No
construction works was conducted on 18 January 2019 under HY/2009/19 around the
monitoring location and nearby traffic noise was observed as major noise source
during monitoring. As such, the exceedance was considered as non-Project
related.
No
construction works was conducted on 25 January 2019 under HY/2009/19 around the
monitoring location and nearby traffic noise was observed as major noise source
during monitoring. As such, the exceedance was considered as non-Project
related.
Reporting
period of February 2019
4.1.9 Two limit level exceedance was recorded
at M6 – Hong Kong Baptist Church Henrietta Secondary School on 30 January and
15 February 2019 in the reporting period.
No
construction works was conducted on 30 January 2019 under HY/2009/19 around the
monitoring location and nearby traffic noise was observed as major noise source
during monitoring. As such, the exceedance was considered as non-Project
related.
No
construction works was conducted on 15 February 2019 under HY/2009/19 around
the monitoring location and nearby traffic noise was observed as major noise
source during monitoring. As such, the exceedance was considered as non-Project
related.
4.2.1
1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a,
CMA4a, CMA5b and CMA6a in the reporting period.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.2.2
Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations is
summarized in Table 4.6 below.
Table
4.6 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA3a |
CWB PRE Site Office |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Reporting
period of December 2018
4.2.3 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of January 2019
4.2.4 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of February 2019
4.2.5 No
action or limit level exceedance was recorded in the reporting period.
Contract no. HY/2009/19 –Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.6
Air monitoring at CMA1b and CMA2a have been implemented with respect to
HY/2009/19 since the marine bore piling works started on 28 Jan 2012. No
exceedance was recorded in the reporting period.
4.2.7
The proposed division of air monitoring stations is summarized in Table
4.8 below.
Table
4.8 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
Reporting
period of December 2018
4.2.8 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of January 2019
4.2.9 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of February 2019
4.2.10 No
action or limit level exceedance was recorded in the reporting period.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
4.2.11 The proposed division of air
monitoring stations are summarized in Table 4.9 below.
Table 4.9 Air Monitoring
Stations for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Reporting
period of December 2018
4.2.12 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of January 2019
4.2.13 No action or limit level exceedance was
recorded in the reporting period.
Reporting
period of February 2019
4.2.14 No action or limit level exceedance was
recorded in the reporting period.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East
4.3.1
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.12 below.
Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
Cooling Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/WSD Wanchai salt water intake / China Resources
Building |
836268.0 |
816020.0 |
Reporting
period of December 2018
4.3.2 1 action level exceedance of turbidity
was recorded at C1 on 28 November 2018 during flood tide in the reporting
period.
Despite
trimming of seawall bedding at TWCR4 under Contract HK/2009/02 was conducted on
the monitoring date, contractor mitigation measure including the use of silt
curtain was in place. In view of the above, it is considered that the
exceedance was not related to Project works. No exceedance was recorded in the
subsequent monitoring on 30 November 2018 ebb tide.
Reporting
period of January 2019
4.3.3 No action or limit level exceedance was
recorded in the January 2019 reporting period.
Reporting
period of February 2019
4.3.4 No
action level exceedance was recorded in the February 2019 reporting period.
Contract no. HK/2012/08
- Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
4.3.5
Water
monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The
proposed division of water monitoring stations are summarized in Table 4.13
below.
Table 4.13
Water Monitoring Stations for Contract
no. HK/2012/08
Station Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings (Wanchai Tower /
Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
|
Reporting
period of December 2018
4.3.6 One action level exceedance of Turbidity
was recorded at WSD19 on 28 November 2018 during flood tide in the reporting
period.
No
marine construction activity under Contract HK/2012/08 was conducted on the
monitoring date. In view of the above, it is considered the exceedance was not
related to Project work. No exceedance was recorded on the subsequent monitoring
on 30 November 2018 ebb tide.
Reporting
period of January 2019
4.3.7 One action level exceedance of suspended
solids was recorded on 25 January 2019 at P5 in the reporting period.
No
marine construction activity was conducted under Contract HK/2012/08 on the
monitoring date while the location of the construction area was at downstream
of monitoring station P5 during monitoring period. In view of the above, it is
considered that the exceedance was not related to Project works.
Reporting
period of February 2019
4.3.8 No action level exceedance was recorded
in the reporting period
4.3.9 Referring to WDII RSS confirmation on
the completion of marine works under HK/2012/08 within the EP-356 area on 2
January 2019 and the completion of the post construction water quality monitoring
(From 2 January 2019 to 30 January 2019), the respective water quality monitoring
stations P1, P3, P4, P5 and WSD19 within EP-356 area was temporarily suspended
since 15 February 2019 onwards.
Contract
no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
4.3.10
Inert
C&D waste and no Non-inert C&D waste were disposed of for the site
works in this reporting period. Details of the waste flow table are summarized
in Table
4.19.
4.3.11
No
Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1-
Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal)
disposed of in this reporting quarter.
Table 4.19 Details of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
3981.5 |
313695.5 |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1515.103 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
NIL |
13860 |
SENT Landfill |
Marine Sediment (Type 1 – Open Sea Disposal), m3
|
NIL |
240222 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 * |
NIL |
146445 (Bulk volume) |
East of Sha Chau |
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
4.3.12
No Inert
C&D waste disposed in this reporting period and no non-inert C&D waste
was disposed in this reporting period. Details of the waste flow table are
summarized in Table 4.20.
4.3.13 No marine sediments Type1- Open Sea Disposal and no
Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine
Disposal in this reporting quarter.
Table 4.20 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
8127.21 |
HY/2010/08 |
NIL |
NIL |
304 |
Ex-PCWA |
NIL |
|
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
NIL |
156909 (Bulk
Volume) |
South of Cheung Chau |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL |
327746 (Bulk
Volume) |
East of Sha Chau |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine Sediment (Type 3 – Special Treatment /
Disposal contained in Geosynthetic Containers) |
NIL |
12640 (Bulk Volume) |
East of Sha Chau |
Dredging from TCBR1W / Maintenance dredging |
Marine Sediment (Type 2 – Confined Marine
Disposal), m3 |
NIL (Bulk Volume) |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern Breakwater of CBTS |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Marine Sediment (Type 2– Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Marine Sediment (Type 3 – Special Treatment /
Disposal contained in Geosynehetic Containers)
, m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Contract
no. HY/2009/19 – Central- WanChai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
4.3.14 No Inert and non-inert C&D waste were disposed
of in this reporting quarter. Details of the waste flow table are summarized in
Table
4.21.
4.3.15 No marine sediments Type1- Open Sea Disposal and no
Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine
Disposal in this reporting quarter.
Table
4.21 Details of Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
355921.04 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
333.14 |
N/A |
Chemical waste disposed, L |
NIL |
2.12 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine
Sediment (Type 2 – Confined Marine Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine Disposal) , m3 |
NIL |
4976.00 |
N/A |
Contract
no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
4.3.16 No Inert and non-inert C&D waste were disposed
of in this reporting quarter. Details of the waste flow table are summarized in
Table
4.22.
4.3.17 No Marine Sediment Type 1 – Open Sea
Disposal (Delicate Sites) & Type 2 – Confined Marine Disposal and Marine
Sediment Type 1 – Open Sea Disposal disposed in this reporting quarter.
Table
4.22 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL NIL |
4131 273 |
TM38 TKO 137 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials disposed, m3 * |
NIL |
400 |
SENT |
Non-inert
C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical
waste disposed, L |
NIL |
NIL |
N/A |
Marine
Sediment (Type 1 – Open Sea Disposal), m3
* |
NIL (Bulk volume) |
31759 (Bulk volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine Disposal) , m3 * |
NIL (Bulk volume) |
108542 (Bulk volume) |
South of The Brothers (from 27 Aug 2013 onwards) |
*Remarks: The details of waste disposal is recorded in calendar month
period.
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
4.3.18 No Inert or non-inert C&D waste was disposed in
this reporting period. Details of the waste flow table are summarized in Table
4.23
4.3.19 No marine Sediment Type 1 – Open Sea
Disposal and Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 –
Confined Marine Disposal disposed in this reporting period, and no Type 3-
Special Treatment disposed in this reporting period.
Table 4.23 Details of Waste Disposal for Contract no. HY/2010/08
Waste
Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL NIL |
95094.759 19739.4 |
TM38 TKO137 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical
waste disposed, L |
NIL |
NIL |
N/A |
Marine
Sediment (Type 1 – Open Sea Disposal) |
NIL |
62559.4 |
South Cheung Chau |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine disposal) |
NIL |
28309.2 |
Brothers Island |
Marine
Sediment (Type 3 – Special Treatment) |
NIL |
7780 |
Brothers Island |
5.0.1. The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 5.1.
Reporting
period of December 2018
5.1.1 One limit level exceedance was recorded at M1a in the
reporting period. After the investigation, the exceedance was concluded as
non-Project related.
Reporting period of January 2019
5.1.2 Two limit level
exceedance was recorded at M6 – Hong Kong Baptist Church Henrietta Secondary
School on 18 and 25 January 2019 in the reporting period. After the investigation,
the exceedance was concluded as non-project related.
Reporting
period of February 2019
5.1.3 Two limit level
exceedance was recorded at M6 – Hong Kong Baptist Church Henrietta Secondary
School on 30 January and 15 February 2019 in the reporting period. After the investigation,
the exceedance was concluded as non-project related.
Reporting
period of December 2018
5.2.1 No action or limit level exceedance was recorded in the reporting
period.
Reporting period of January 2019
5.2.2 No action or limit level exceedance was recorded in the reporting
period.
Reporting period of February 2019
5.2.3 No action or limit level exceedance was recorded in the reporting
period.
5.3.1
Referring
to WDII RSS confirmation on the completion of marine works under HK/2012/08 within
the EP-356 area on 2 January 2019 and the completion of the post construction
water quality monitoring (From 2 January 2019 to 30 January 2019), the
respective water quality monitoring stations P1, P3, P4, P5 and WSD19 within EP-356
area was temporarily suspended since 15 February 2019 onwards.
Reporting period of December
2018
5.3.2
Two action
level exceedances of turbidity were recorded in the reporting period. After the
investigation, the exceedances recorded were considered as non-project related.
Reporting period of January 2019
5.3.3
One action
level exceedance of suspended solids was recorded in the reporting period.
After the investigation, the exceedance was concluded as non-project related.
Reporting period of February 2019
5.3.4
No action
or limit level exceedance was recorded in the reporting period
5.4.1 There was no non-compliance from the
site audits in the reporting period. During environmental site inspections
conducted during the reporting period, minor deficiencies were note.
5.5.1
There was
no non-compliance from the site audits in the reporting period.
6.0.1. One environmental complaint was received
in the January 2019 reporting period.
An EPD complaint was referred to the ET on 16 January 2019 (CASE Ref: H08/RS/00001488-19,
H08/RS/00001532-19, and H08/RS/00001663-19). The complainant reported that
milky water discharge was found at the Victoria Harbour, near Causeway Bay Typhoon
Shelter on 12 January 2019. ET confirmed with the WDII Resident Site Staff that
the concerned area was located out of the site area of Contract No. HK/2009/02
and the Contractor of HK/2009/02 had no activity at the area concerned on 12
January 2019. ET confirmed with the CWB Resident Site Staff that no construction
works was conducted by the contractor of HY/2010/08 at Victoria Harbour, near
Causeway Bay Typhoon Shelter on 12 January 2019 at around noon.
Despite no construction activity was conducted under Contract HK/2009/02
and HY/2010/08 on the concerned date and location as confirmed with
corresponding Resident Site Staff, in view of public concern, the Contractor of
Contract HK/2009/02 and HY/2010/08 were reminded to review the on-site drainage
system and the operation of wastewater treatment system. The Contractor of
Contract HK/2009/02 and HY/2010/08 were also reminded to provide mitigation measure
such as deployment of silt curtain to enclose the works area if any marine
activity to be conducted at the concerned area.
6.0.2.
The details of cumulative complaint
log and summary of complaints are presented in Appendix
6.1.
6.0.3. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting quarter |
49 |
December
2018 to February 2019 |
1 |
Project-to-Date |
50 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.2. According
to the Final EM&A Report of Central Reclamation
Phase III (CRIII) for Contract HK 12/02, the major construction activities were
completed by end of January 2014 and no construction activities were undertaken
thereafter and the water quality monitoring was completed in October 2011 and
no Project-related exceedance was recorded for air and noise monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According
to the construction programme of Central-Wanchai Bypass at Wanchai West at
the Central Reclamation Phase III area include roadworks, drainage, seawall
coping and junction modification were performed in February 2019 reporting
period. As
no project related exceedance were recorded during the reporting period,
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was considered as
insignificant.
7.0.4. According to the construction programme
of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activities under Wan Chai
Development Phase II were road and drains construction and TWCR4 reinstatement
at Wan Chai. The major construction activities under Central-Wan Chai Bypass and
Island Eastern Corridor Link Projects were ventilation building ABWF works and
junction modification at Central; road works, drainage improvement work,
utility diversion works and landscape works at Victoria Park; bridge noise
enclosure installation works, road works, drainage works, soft landscape works
and ventilation building ABWF work at North Point area in the reporting period.
In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass
and Island Eastern Corridor Link projects were observed undertaken at Wan Chai
North and North Point area.
7.0.5. No significant air impact from
construction activities was anticipated in the reporting month. Besides, no
project related exceedance was recorded during the air and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) was insignificant.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2.
There was
no non-compliance from the site audits in the December 2018, January and
February 2019 reporting period.
8.0.3.
One
environmental complaint was received in the January 2019 reporting period
8.0.4. The construction programmes
of individual contracts are provided in Appendix 7.1.